The new headquarters of your stainless steel tubes
Watch the development
of the new building and any new updates here.
We are looking forward to being at your service in 2021 with our
precision tubes from Lupfig.

11.03.2021. The east facade with staircase grows in height.

05.02.2021 3rd upper floor, the ceiling is completed.

11.01.2021 Start of wall formwork for the 3rd floor.

02.11.2020 The roof over the ground floor is finished.

14.10.2020 Assembly of the hollow boards

09.10.2020 Assembly of the delta beam

18.09.2020 Entry ramp is concreted

03.09.2020 Foundation is finished

21.08.2020 Slab formwork 1st stage UG

28.07.2020 The construction site during the summer holidays

14.07.2020 Flooring and walls

18.06.2020 The excavation work progresses

13.06.2020 The construction crane has arrived

07.06.2020 Preparing for the crane

20.05.2020 The excavation work begins

11.03.2021. The east facade with staircase grows in height.

05.02.2021 3rd upper floor, the ceiling is completed.

11.01.2021 Start of wall formwork for the 3rd floor.

02.11.2020 The roof over the ground floor is finished.

14.10.2020 Assembly of the hollow boards

09.10.2020 Assembly of the delta beam

18.09.2020 Entry ramp is concreted

03.09.2020 Foundation is finished

21.08.2020 Slab formwork 1st stage UG

28.07.2020 The construction site during the summer holidays

14.07.2020 Flooring and walls

18.06.2020 The excavation work progresses

13.06.2020 The construction crane has arrived

07.06.2020 Preparing for the crane

20.05.2020 The excavation work begins